Question 88Asked in RRB JE CBT-1, 17 Dec 2024, Shift 2 (12:45 PM)

35 men can do a piece of work in 48 days. The number of men required to complete the same work in 21 days is:

  1. A72
  2. B80
  3. C77
  4. D79
Show answerHide answer

Correct answer: (B) 80

From RRB JE CBT-1 PYQ 17 Dec 2024, Shift 2 (12:45 PM)