Question 6Asked in RRB JE CBT-1, 18 Dec 2024, Shift 2 (12:45 PM)

A and B can do a piece of work in 2 days and 42 days, respectively. The number of days [Correct to one decimal place] required to complete the work if both…

A and B can do a piece of work in 2 days and 42 days, respectively. The number of days [Correct to one decimal place] required to complete the work if both A and B work together is:
  1. A1.9
  2. B5.1
  3. C3.3
  4. D1.3
Show answerHide answer

Correct answer: (A) 1.9

From RRB JE CBT-1 PYQ 18 Dec 2024, Shift 2 (12:45 PM)

This is question 6 of RRB JE CBT-1 PYQ 18 Dec 2024, Shift 2 (12:45 PM). See all questions of this paper with answers, or attempt the paper as a timed online test to get your score and all-India rank.