Question 29Asked in DSSSB TGT Computer Science (Technical), 1 Aug 2021, Shift 3

A railway crossing has 4 railway tracks. If a train comes on at least 1 of the tracks, the crossing has to be closed. Which gate can be used to implement this?

  1. ANAND
  2. BNOR
  3. COR
  4. DAND
Show answerHide answer

Correct answer: (C) OR

Explanation

The crossing must close if any one or more of the 4 tracks has a train, i.e. output 1 when at least one input is 1, which is the OR function.