Question 70Asked in UGC NET Computer Science, June 2015 (Paper II & III, Selected Questions)

Requirements prioritization and negotiation belongs to :

  1. ARequirements validation
  2. BRequirements elicitation
  3. CFeasibility study
  4. DRequirements reviews
Show answerHide answer

Correct answer: (B) Requirements elicitation

Explanation

Elicitation is the process of gathering, understanding and documenting requirement. Prioritization and negotiation are key activities within the elicitation process to ensure a feasible and well defined set of requirements for the project. Requirements Validation– This is the process of checking if the gathered requirements are correct, complete and consistent. Feasibility study– This is an assessment of whether a project is viable and achievable, considering factors like cost, resources and technology. Requirements Reviews– These are formal assessments of the requirements documentation, typically conducted by stakeholders and experts, to identify potential issues and ensure quality.

From UGC NET Computer Science PYQ, June 2015 (Paper II & III, Selected Questions)

This is question 70 of UGC NET Computer Science PYQ, June 2015 (Paper II & III, Selected Questions). See all questions of this paper with answers, or attempt the paper as a timed online test to get your score and all-India rank.