The major shortcoming of waterfall model is :
Show answerHide answer
Correct answer: (A) The difficulty in accommodating changes after requirement analysis
Explanation
The main drawback of the waterfall model is the difficulty of accommodating change after the process is under way. (1) Difficult to address change: Inflexible partitioning of the project into distinct stage makes it difficult to respond to changing customer requirements. Therefore, this model is only appropriate when the requirement are well understood and changes will be fairly limited during the design process