Which of the following is NOT true about the Waterfall model?
Show answerHide answer
Correct answer: (B) High cost
Explanation
The waterfall model is simple and considered low cost for well-defined projects, but it takes long and carries high risk. So "high cost" is the statement that is not true of it.