Question 53Asked in DSSSB TGT Computer Science (Technical), 1 Aug 2021, Shift 3

Which of the following statement(s) is/are correct regarding software project management?

Which of the following statement(s) is/are correct regarding software project management? I. PERT charts can be derived automatically from Gantt charts. II. Gantt charts cannot be automatically derived from PERT charts.
  1. AOnly I
  2. BOnly II
  3. CBoth I and II
  4. DNeither I nor II
Show answerHide answer

Correct answer: (D) Neither I nor II

Explanation

A Gantt chart can be derived automatically from a PERT chart, but a PERT chart cannot be derived from a Gantt chart because Gantt charts lack task dependencies. Both statements are false.

From DSSSB TGT Computer Science PYQ (Technical), 1 Aug 2021, Shift 3