Which of the following statement(s) is/are correct regarding software project management?
Which of the following statement(s) is/are correct regarding software project management?
I. PERT charts can be derived automatically from Gantt charts.
II. Gantt charts cannot be automatically derived from PERT charts.
Show answerHide answer
Correct answer: (D) Neither I nor II
Explanation
A Gantt chart can be derived automatically from a PERT chart, but a PERT chart cannot be derived from a Gantt chart because Gantt charts lack task dependencies. Both statements are false.