Question 35Asked in UGC NET Computer Science, June 2015 (Paper II & III, Selected Questions)

Which one from the following is highly associated activity of project planning?

  1. AKeep track of the project progress
  2. BCompare actual and planned progress and costs
  3. CIdentify the activities, milestones and deliverables produced by a project
  4. DBoth (b) and (c)
Show answerHide answer

Correct answer: (C) Identify the activities, milestones and deliverables produced by a project

Explanation

Project planning means identifying the activities, milestones and deliverables produced by a project. It is commonly perceived as creating a Gantt chart, which is incorrect; a Gantt chart is merely a visual representation of the project schedule.

From UGC NET Computer Science PYQ, June 2015 (Paper II & III, Selected Questions)

This is question 35 of UGC NET Computer Science PYQ, June 2015 (Paper II & III, Selected Questions). See all questions of this paper with answers, or attempt the paper as a timed online test to get your score and all-India rank.