Question 24Asked in UGC NET Computer Science, June 2014 (Paper II & III, Selected Questions)

Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets?

  1. ADetailed multi source cost and schedule estimation.
  2. BDesign cost
  3. CIncremental development
  4. DInformation hiding
Show answerHide answer

Correct answer: (D) Information hiding

Explanation

Risk management is the Process of identifying, controlling threats to an organization's capital and earning. Risk management can be considered as dealing with the possibility and actual occurrence of those events that are not regular expected and information hiding is the principle of segregation of the design decision in a computer program that are most like to change, thus protecting other parts of the program from extensive modification if the design decision is changed.

From UGC NET Computer Science PYQ, June 2014 (Paper II & III, Selected Questions)

This is question 24 of UGC NET Computer Science PYQ, June 2014 (Paper II & III, Selected Questions). See all questions of this paper with answers, or attempt the paper as a timed online test to get your score and all-India rank.