Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets?
Show answerHide answer
Correct answer: (D) Information hiding
Explanation
Risk management is the Process of identifying, controlling threats to an organization's capital and earning. Risk management can be considered as dealing with the possibility and actual occurrence of those events that are not regular expected and information hiding is the principle of segregation of the design decision in a computer program that are most like to change, thus protecting other parts of the program from extensive modification if the design decision is changed.