According to PUTNAM, the project effort is inversely proportional to the fourth power of the development time. Doubling the development schedule for a 100…
According to PUTNAM, the project effort is inversely proportional to the fourth power of the development time. Doubling the development schedule for a 100 Person-Month (PM) project would reduce the project effort to
Show answerHide answer
Correct answer: (D) 6.25 PM
Explanation
Effort ∝ 1/t⁴, so doubling the time divides effort by 2⁴ = 16: 100 ÷ 16 = 6.25 PM.