Question 73

Project risk factor is considered in

  1. AWaterfall model
  2. BPrototyping model
  3. CSpiral model
  4. DIterative enhancement model
Show answerHide answer

Correct answer: (C) Spiral model

Explanation

Boehm's spiral model explicitly analyses project risks in every cycle (a risk analysis quadrant), unlike the waterfall or prototyping models.