______ activities are at the very core of project completion work tasks, whereas ______ activities are not mandatory.

Show answerHide answer
Correct answer: (C) Functional, non-functional
Explanation
Functional activities directly produce the required features and are essential to complete the project's work tasks. Non-functional activities support quality aspects and are treated as not mandatory for completion.