Question 116Asked in DSSSB TGT Computer Science, 25 Jun 2023, Shift 2 (12:30 PM)

______ activities are at the very core of project completion work tasks, whereas ______ activities are not mandatory.

______ activities are at the very core of project completion work tasks, whereas ______ activities are not mandatory.
  1. ARequirements, arbitrary
  2. BFramework, umbrella
  3. CFunctional, non-functional
  4. DNon-functional, functional
Show answerHide answer

Correct answer: (C) Functional, non-functional

Explanation

Functional activities directly produce the required features and are essential to complete the project's work tasks. Non-functional activities support quality aspects and are treated as not mandatory for completion.