Question 43Asked in DSSSB TGT Computer Science (Technical), 7 Aug 2021, Shift 2

Which of the following is not a project estimation technique in software engineering?

  1. AEmpirical Techniques
  2. BHeuristic Techniques
  3. CAnalytical Techniques
  4. DPrototyping Techniques
Show answerHide answer

Correct answer: (D) Prototyping Techniques

Explanation

Project estimation techniques are empirical, heuristic and analytical. Prototyping is a development model, not an estimation technique.

From DSSSB TGT Computer Science PYQ (Technical), 7 Aug 2021, Shift 2