Which of the following statement(s) is/are true regarding PERT chart in software project management?
Which of the following statement(s) is/are true regarding PERT chart in software project management?
I. PERT charts consists of a network of boxes and arrows.
II. In PERT chart, the boxes represent activities and the arrow represents task dependencies.
Show answerHide answer
Correct answer: (C) Both I and II
Explanation
A PERT chart is a network of boxes (or nodes) and arrows. The boxes are activities and the arrows show the dependencies between them, so both statements are true.