The COCOMO model was developed by:
Show answerHide answer
Correct answer: (B) Barry Boehm
Explanation
COCOMO = Constructive Cost Model (1981).
Correct answer: (B) Barry Boehm
Explanation
COCOMO = Constructive Cost Model (1981).