Question 7Asked in BPSC TRE 1.0 (2023) Computer Science Class 11-12 + 18 more papers

Two persons A and B complete a task in 15 days, when they work together. Person A completes the task in 20 days if he works alone. How many days will B take…

Two persons A and B complete a task in 15 days, when they work together. Person A completes the task in 20 days if he works alone. How many days will B take to finish the task alone?
  1. A35 days
  2. B25 days
  3. C60 days
  4. DMore than one of the above
  5. ENone of the above
Show answerHide answer

Correct answer: (C) 60 days

Explanation

B's one-day work = 1/15 − 1/20 = (4 − 3)/60 = 1/60, so B alone takes 60 days.

From BPSC TRE 1.0 (2023) Computer Science Class 11-12 — Previous Year Paper

This is question 7 of BPSC TRE 1.0 (2023) Computer Science Class 11-12 — Previous Year Paper. See all questions of this paper with answers, or attempt the paper as a timed online test to get your score and all-India rank.